We experienced a problem today caused by a rogue unit price on the Schedule of Values that was entered incorrectly. The incorrect unit price was brought over into a Draw Request before we realized the problem.
It is understandable that the Draw Request instances the Schedule of Values at the time of its creation, but it would be exceedingly helpful if there was a button option or utility that could be utilized to force the Draw Request to refresh its instance from the current Schedule of Values. This way if Accounts Receivable or Management needs to make a minor adjustment/correction to the Schedule of Values, they will be able to push those changes to the current draw request without jumping through all sorts of hoops.
Company | Traffic & Lighting Systems, LLC |
Job Title / Role | Technology Consultant |
I need it... | Yesterday...Come on already |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
We currently have a contract where Phase 1 is broken out into a detailed SOV and Phase 2 is not - it is represented as a single line item to be detailed out later as it will not start for a few months. While the client is ok with this, Spectrum is not, therefore we cannot use Draw Request Entry for this contract at any time for the duration of the job. I can change the SOV without an issue, but that change will not be reflected in Draw Request once App01 has been entered and posted.